Issue - decisions

Bargate Scheme - Community Infrastructure Levy Relief

13/09/2021 - Bargate Scheme - Community Infrastructure Levy Relief

Modified recommendations:

 

(i)  Consider the 4 options set out in the report;

(ii)  Accept a partial claim as set out in Option 1 below, whereby a significantly reduced CIL contribution is sought given the exceptional heritage circumstances associated with the Bargate Centre’s context and redevelopment proposals; and

(iii)  Allocate the outstanding £520k CIL payment towards maintenance and repair works to the North Town Walls.