That the proposed new decommissioning order is approved. This would include the following changes to the current, approved decommissioning order:
1. To bring forward the start date for decommissioning 166-186 Meggeson Avenue (Plot 5) by circa 1 month.
2. To delay the start date for decommissioning 144-164 Meggeson Avenue (Plot 5) by circa 15 months from November 2020 to February 2022. However, it is possible this may be shorter than 15 months and instead be an 8-month delay.
3. To bring forward the start date for decommissioning 107-125 Meggeson Avenue (including the row of shops) by circa 17 months.
4. To bring forward the start date for decommissioning 1 – 87 Kingsdown way (Plot 7) by circa 13 months.
5. To delay the start date for decommissioning 289-331 Meggeson Avenue (Plot 13) by circa 13 months.
6. To delay the start date for decommissioning 254-318 Meggeson Avenue (Plot 12) by circa 13 months.
(See Appendix 1 Slide 7 existing and proposed order and Appendix 5 Proposed Order 2021)