HRA Capital Programme Approval - Supported Housing 2-storey Walkway Repairs

20/09/2016 - HRA Capital Programme Approval - Supported Housing 2-storey Walkway Repairs

(i)  To approve the increase of the budget for Supported Housing 2 storey walk-up blocks by £656,000 to enable walkway repairs across the city to be fully completed, funded from a reduction in the budgets for Communal Area Works (£340,000), Damp Proof Membrane Renewals (£118,000), Structural Works (£98,000) and Studio Conversions (£100,000) within the HRA Capital Programme.

 

(ii)  To approve additional capital expenditure of £656,000 in 2016-17, in accordance with Finance Procedure Rules, on Supported Housing 2 storey walk-up blocks.