74 General Fund Capital Budget 2012/13 to 2014/15 PDF 109 KB
Report of the Cabinet Member for Resources, Leisure and Culture seeking approval to recommend to Council the updated Capital Programme, attached.
Additional documents:
Minutes:
DECISION MADE: (Ref: CAB 11/12 7587)
On consideration of the report of the Cabinet Member forResources, Leisure and Culture and having received representations from Members of the Council, Cabinet agreed to do the following:
Recommend that Full Council:
i) Approve the revised General Fund Capital Programme, which totals £168.5M (as detailed in paragraph 4) and the use of resources.
ii) Approve the forecast over programming of £751,000 as detailed in paragraph 11, which is within the previously approved tolerances and can be compared to the figure reported to Council in September of £8.1M.
iii) Note that the reduction in the funding deficit is largely down to additional or increased forecast future capital receipts where the timing and exact value is to a degree uncertain.
iv) Note the forecast funding deficit in 2011/12 as detailed in paragraph 15 that is likely to require temporary borrowing, the revenue implications of which have been reflected in the budget forecast for the General Fund.
v) Add £4,084,000 to the Environment & Transport capital programme in 2012/13 for Roads which is currently to be funded by direct revenue financing (£2,672,000), Council Resources (£1,272,000 unsupported borrowing), on-street parking surplus contributions (£90,000) and other revenue contributions (£50,000).
vi) Add £408,000 to the Environment & Transport capital programme for the Salix Energy Efficiency scheme in 2012/13 to be funded by government grants.
vii) Add £519,000 to the Leisure & Culture capital programme phased £110,000 in 2012/13, £170,000 in 2013/14 and £239,000 in 2014/15 to carry out essential works at the Guildhall to be funded by Council Resources.
viii) Add £805,000 to the Adult Social Care & Health capital programme for essential refurbishment and improvements at care homes in 2012/13 to be funded by government grant.
ix) Delegate authority to the Chief Finance Officer in consultation with the Executive Director of Environment and following consultation with the Cabinet Member for Environment & Transport and the Cabinet Member for Resources, Leisure & Culture to add Salix schemes to the capital programme up to the value of £100,000 per year, funded from a self-sustaining budget created from savings generated.
x) Note that the revised General Fund Capital Programme takes into account the Comprehensive Spending Review (CSR) for 2011/12 and future years.