45 INTEGRATED TRANSPORT & HIGHWAYS PROGRAMME 2021/22 - APPROVAL TO SPEND PDF 356 KB
Report of the Cabinet Member for Growth seeking approval to spend on the Integrated Transport and Highways Programme 2021/22.
Additional documents:
Minutes:
Report of the Cabinet Member for Growth seeking approval to spend the Integrated Transport and Highways Programme 2021/22.
RESOLVED:
(i) That the updated capital programme for Integrated Transport and Highways, the revised financing of the programme and the associated capital spend for 2021/22, including amendments detailed within this report and in accordance with financial procedure rules, of £74.55M as detailed in paragraph 17 and Appendix 1 be approved;
(ii) That the overall budget addition of £2.33M, to the Place capital programme funded by government grant and S106 developer contributions, as detailed in paragraph 18 and Appendix 1 be approved;
(iii) That budget virements between existing schemes within the programme as detailed in paragraph 19 and Appendix 1 be approved; and
(iv) That the details of the projects within Transforming Cities Programme and Future Transport Zone Programme as detailed in Appendices 2 and 3 be noted.
33 Updates to the Highways and Transport Capital Programme PDF 356 KB
Report of the Cabinet Member for Growth, detailing updates to the five-year Highways and Transport investment programme.
Additional documents:
Minutes:
DECISION MADE: (CAB 21/22 32686)
On consideration of the report of the Cabinet Member for Growth, Cabinet agreed the following:
(i) To note the updated capital programme for Integrated Transport and Highways, the revised financing of the programme and the associated capital spend for 2021/22, including amendments detailed within this report and in accordance with financial procedure rules, of £74.55M as detailed in paragraph 17 and Appendix 1.
(ii) To note the overall budget addition of £2.33M, to the Place capital programme funded by government grant and S106 developer contributions, as detailed in paragraph 18 and Appendix 1.
(iii) To note budget virements between existing schemes within the programme as detailed in paragraph 19 and Appendix 1.
(iv) To note the details of the projects within Transforming Cities Programme and Future Transport Zone Programme as detailed in Appendices 2 and 3.