Issue - meetings

HRA Scheme Approval 2015/16 to 2019/2020

Meeting: 20/05/2015 - Council (Item 21)

21 HRA Scheme Approval 2015/16 to 2019/20 pdf icon PDF 216 KB

Report of the Cabinet Member for Housing and Sustainability seeking approval of expenditure for Housing Revenue Account funded projects, attached.

Additional documents:

Minutes:

The report of the Cabinet Member for Housing and Sustainability was submitted seeking approval of expenditure for Housing Revenue Account funded projects.

 

RESOLVED

 

 

(i)  To approve in accordance with Financial Procedure Rules capital expenditure of £32,890,000 phased as follows:

 

  £2,806,000 in 2015/16

  £22,233,000 in 2016/17

  £3,720,000 in 2017/18

  £2,150,000 in 2018/19

  £1,981,000 in 2019/20

For which provision exists within the Warm and Energy Efficient, Well Maintained Communal Facilities, Safe, Wind and Weather tight and Modern Facilities sections of the HRA Capital Programme as detailed in the table below

 

Safe, Wind and Weather Tight

2015/16

2016/17

2017/18

2018/19

2019/20

Total

 

000s

000s

000s

000s

000s

000s

Roof Finish – Flat

0

642

1168

1000

0

2810

Structural Works

0

4398

0

0

0

4398

Total for Safe, Wind and Weather Tight

0

5040

1168

1000

0

7208

 

 

 

 

 

 

 

Modern Facilities

 

 

 

 

 

 

Electrical Systems

2158

2811

0

0

0

4969

Housing Refurbishment Programme

0

7946

0

0

0

7946

Total for Modern Facilities

2158

10757

0

0

0

12915

 

 

 

 

 

 

 

Well Maintained Communal Facilities

 

 

 

 

 

 

Decent Neighbourhoods Improvement

648

750

1102

0

0

2,500

Lift Refurbishments

0

700

1450

1150

1981

5281

Total for Well Maintained Communal Facilities

648

1450

2552

1150

1981

7781

 

 

 

 

 

 

 

Warm and Energy Efficient

 

 

 

 

 

 

External Cladding

0

4986

0

0

0

4986

Total for Warm and Energy Efficient

0

4986

0

0

0

4986

 

 

 

 

 

 

 

TOTAL

2,806

22,233

3,720

2,150

1,981

32,890

 


Meeting: 21/04/2015 - Cabinet (Item 79)

79 HRA Scheme Approval 2015/16 to 2019/2020 pdf icon PDF 216 KB

Report of the Cabinet Member for Housing and Sustainability seeking approval of expenditure for Housing Revenue Account funded projects, attached.

Additional documents:

Minutes:

DECISION MADE: (Ref: CAB 14/15 14618)

On consideration of the report of the Cabinet Member for Housing and Sustainability, Cabinet agreed the following:

 

To approve in accordance with Financial Procedure Rules expenditure of £4,751,000 phased as follows:

  • £1,548,000 in 2015/16
  • £3,203,000 in 2016/17

Provision for which exists within the Safe, Wind and Weather tight; Modern Facilities; Well Maintained Communal Facilities and Warm and Energy Efficient sections of the HRA Capital Programme as detailed in the table below.

 

Safe, Wind and Weather Tight

2015/16

2016/17

2017/18

2018/19

2019/20

Total

 

000s

000s

000s

000s

000s

000s

Renew Canopies

10

130

0

0

0

140

Renew Porches

10

200

0

0

0

210

Windows

0

978

0

0

0

978

Wall Structure and Finish

134

372

0

0

0

506

Total for Safe, Wind and Weather Tight

154

1680

0

0

0

1834

 

 

 

 

 

 

 

Modern Facilities

 

 

 

 

 

 

Programme Management Fees

59

643

0

0

0

702

Tenant Alterations Budget

7

268

0

0

0

275

Total for Modern Facilities

66

911

0

0

0

977

 

 

 

 

 

 

 

Well Maintained Communal Facilities

 

 

 

 

 

 

New Build Lift at Block 1-62 Rozel Court

500

0

0

0

0

500

Total for Well Maintained Communal Facilities

500

0

0

0

0

500

 

 

 

 

 

 

 

Warm and Energy Efficient

 

 

 

 

 

 

Landlord Meter Conversion

189

194

0

0

0

383

Renewable Energy Sources

300

318

0

0

0

618

Communal Shed/Store Areas

0

50

0

0

0

50

Renew Communal Windows

50

50

0

0

0

100

Utility Supplies Communal

289

0

0

0

0

289

Total for Warm and Energy Efficient

828

612

0

0

0

1440

 

 

 

 

 

 

 

TOTAL

1,548

3,203

0

0

0

4,751