THE GENERAL FUND CAPITAL PROGRAMME 2016/17 TO 2020/21

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

(i)  To note the revised General Fund Capital Programme 2016/17 to 2020/21, which totals £145.42M (as detailed in paragraph 4) and the associated use of resources.

(ii)  To note that £0.28M has been added to the overall programme, with approval to spend, under delegated powers (£0.26M 2016/17 and £0.02M 2017/18). These additions are detailed in paragraph 6 and Appendix 2.

(iii)  To note that £0.63M has been removed from the overall programme, as detailed in paragraph 6 and Appendix 2.

(iv)  To note that £0.01M has been rephased from 2017/18 to 2016/17 within the Transport portfolio, as detailed in paragraph 11 and Appendix 3.

(v)  To note that the revised General Fund Capital Programme is based on prudent assumptions of future Government Grants to be received.

(vi)  To note the changes to the programme, as summarised in Appendix 2 and described in detail in Appendix 3.

(vii)  To note that the forecast position at Quarter 1 is £121.18M, resulting in a potential underspend of £24.24M, as detailed in paragraph 13 and Appendix 4.

Reasons for the decision:

The Capital Programme is now reviewed on a quarterly basis in accordance with the Council’s Capital Strategy. The forecast position is reported to the Council Capital Board with any required programme update reported to Cabinet and Council for approval. This is required to enable schemes in the programme to proceed and to approve additions and changes to the programme. There are currently no additions to the programme, therefore this paper is for information only.

Alternative options considered:

The update of the Capital Programme is undertaken within the resource constraints imposed on it.  No new schemes can be added unless specific additional resources are identified.  Alternative options for new capital spending are considered as part of the budget setting process in the light of the funding available and the overall financial position.

Report author: Madeleine Modha

Publication date: 16/08/2016

Date of decision: 16/08/2016

Decided at meeting: 16/08/2016 - Cabinet

Effective from: 25/08/2016

Accompanying Documents: