Decision details

*Southampton Permit Scheme for management of roadworks and other activities on the road network

Decision Maker: Cabinet

Status: Decision has been rejected

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To consider the report of the Cabinet Member for Environment and Transport to implement the Southampton Permit Scheme (SPS). The scheme seeks to ensure that future road works and activities on the road network are planned and coordinated under The Traffic Management Act (TMA) 2004 which would improve coordination and reduce disruption on the network.

Decision:

(i)  To approve the submission of the Southampton Permit Scheme application (Scheme as set out in Appendix 1) to the Department of Transport requesting approval of the scheme design;

(ii)  To approve that the Southampton Permit Scheme should be a full scheme that applies to all works on all roads and requires a fee to be paid by Statutory Undertakers for all works on all roads per the fee schedule set out in the Scheme attached at Appendix 1;

(iii)  To delegate to The Head of Transport, Highways and Parking the ability to amend the scheme prior to submission and to take all decisions regarding the operational aspects of the project; and

(iv)  To note that a further report will be brought to Cabinet later in the year to consider the Department of Transport approval of the scheme design and approve the implementation of the scheme.

Reasons for the decision:

1.  The Department of Transport requires a full submission in order that they can consider the scheme design prior to preparing a Statutory Instrument (SI) to empower the scheme.

2.  A full scheme will ensure that the Council has control over the entire highways network and is able to manage all works and qualifying activities.

3.  There are a number of operational and set up decisions required to implement the scheme.

4.  The Department of Transport will give the Council 28 days to accept the approved scheme and agree a start date which must be before 31st March 2015.

Alternative options considered:

Option 1: Do Nothing

 

This would involve retaining the existing ‘Notice’ System with minimum statutory controls. This provides greater flexibility for statutory undertakers and works promoters to minimise their costs. This flexibility is due to the large window within which works promoters can plan to carry out their works. There is evidence that some over order so as to keep their labour busy and then cancel the notices they don’t need. This leads to last minute changes with confusion and disruption.

 

The existing scheme has less coordination powers for works within the highway. Only limited information, which is subject to change without consent, is available to other road users. Works often disrupt bus services and lead to additional costs to run extra/replacement services as a result.

 

Option 2: Permits and Notices

 

This would involve having Chargeable Permits on 0, 1& 2 Category Roads and Traffic Sensitive Streets, whilst retaining Notices (as existing) for 3& 4 Category Roads and non Traffic Sensitive Streets.

 

This would provide greater control on the strategic road network, including all Principal Roads, Main Distributor, Local Access, HGV Access routes and all bus routes. This is likely to reduce the number of street works on the strategic road network, which will reduce disruption and burden to business and other road users. Permitted works would demand more detailed advance information enabling better assessment of the impact of the proposed works.

 

However, only partial cost recovery would be possible. Only costs associated with dealing with Permits issued to statutory undertakers are recovered through fees. The Notice regime would still be non-chargeable.

 

With two systems in operation, road works on the majority of the road network, including nearly all urban roads would still only be coordinated by agreement with limited statutory powers available to the Council to improve coordination / communications etc.

 

Option 3: Permits (Chargeable and Deemed)

 

This would involve having Chargeable Permits required on 0,1,& 2 Category Roads and Traffic Sensitive Streets, with non-chargeable ‘Deemed’ Permits required on 3 & 4 category Roads and non Traffic Sensitive Streets.

 

One system would be in operation with Full Permit Powers (controls to force coordination, time / duration of works etc) available to the Council. This is likely to reduce the number of works on the road network, which will reduce disruption and burden to business and other road users.

 

However, some costs are still borne by the Council in relation to dealing with works on non hierarchy roads. Only partial cost recovery would be possible.

Other Relevant Matters Concerning the Decision:

None.

Report author: John Harvey

Publication date: 21/10/2014

Date of decision: 21/10/2014

Decided at meeting: 21/10/2014 - Cabinet

Accompanying Documents: