Decision details

The General Fund Capital Programme 2013/14 to 2016/17

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

i)  To approve the revised General Fund Capital Programme, which totals £132.5M (as detailed in paragraph 4) and the associated use of resources.

ii)  To note the changes to the programme as summarised in Appendix 2 and described in detail in Appendix 3.

iii)  To note the slippage and re-phasing as described in detail in Appendix 3.

iv)  To add £2,652,000 to the Environment & Transport Capital Programme in 2014/15 for the Roads Programme, funded by direct revenue financing.

v)  To add £350,000 to the Environment & Transport Capital Programme in 2014/15 for the purchase of compact sweepers, funded by Council Resources.

vi)  To note that the revised General Fund Capital Programme is based on prudent assumptions of future Government Grants to be received, and that announcements made as part of the Comprehensive Spending Review for 2015/16 and the provisional local government finance settlement have been appropriately reflected in the proposed programme presented for approval.

vii)  To note that additional temporary borrowing taken out in 2010/11 and 2011/12 due to cash flow issues, now totalling £9.4M, is expected to be repaid by the end of 2014/15 when anticipated capital receipts are finally forecast to be received.

viii)  To note that in addition to the forecast capital receipts that are assumed as a key element of funding the capital programme presented for approval, there may be additional receipts which will flow from the sale of assets.  It was anticipated that towards the end of 2013/14 it would be possible to better estimate the amount and timing of any forecast additional receipts but this cannot be completed until the disposal programme which is currently under review is finalised.

ix)  To note the financial and project issues which are set out in paragraphs 29 to 34 and detailed in Appendix 3 for each Portfolio.

Reasons for the decision:

The update of the Capital Programme is undertaken twice a year in accordance with Council Policy and is required to enable schemes in the programme to proceed and to approve additions and changes to the programme.

Alternative options considered:

The update of the Capital Programme is undertaken within the resource constraints imposed on it.  No new schemes can be added unless specific additional resources are identified.  Alternative options for new capital spending are considered as part of the budget setting process in the light of the funding available and the overall financial position.

Report author: Andy Lowe

Publication date: 04/02/2014

Date of decision: 04/02/2014

Decided at meeting: 04/02/2014 - Cabinet

Effective from: 13/02/2014