Issue - decisions

Decommissioning and Acquisition polices and the Decommissioning Plan for Townhill Park Regeneration

14/11/2017 - Decommissioning and Acquisition polices and the Decommissioning Plan for Townhill Park Regeneration

(i)  To consider and determine the proposals in light of the report on the outcome of the consultation and the comments received in response to that consultation.

(ii)  Subject to (i) above, to review and accept the proposed revisions to the Draft Decommissioning of Housing Stock Policy and the Draft Acquisition and Compulsory Purchase Orders Policy as detailed in sections 16 and 17 of this paper:

a) To amend the Draft Decommissioning Policy at section 33 to provide clarification on tenants’ right to return.

b) To amend the Draft Decommissioning of Housing Stock Policy and the Draft Acquisition and Compulsory Purchase Order Policy to remove the offer of increased compensation payments to incentive voluntary agreements.

 

(iii)  Subject to (i) and (ii) above, to approve the proposed Decommissioning of Housing Stock Policy and the proposed Acquisition and Compulsory Purchase Orders Policy contained in Appendix 1 and 2.

(iv)  Subject to receipt of Secretary of State consent where required, To approve the proposed Decommissioning Plan for the remaining properties in Townhill Park Regeneration Scheme contained in Appendix 3.

(v)  Subject to approval of (iv), to delegate to the Head of Capital Assets, following  consultation with the Leader and Service Director, Adults, Housing and Communities approval of further changes to the order of the Decommissioning Plan for Townhill Park Regeneration Scheme contained in Appendix 3, subject to any necessary statutory consultation.